How Long Does a Kitchen Remodel Take in Atlanta?

The short answer: most full custom kitchen remodels take roughly 6–10 weeks from the day you approve the design. Design and approvals take about 1–3 weeks, custom production follows, and the on-site work — demolition plus installation — takes about 2–4 weeks. And here is the part that matters most: you are only without a kitchen during those final on-site weeks, not for the whole project.

Below is the realistic timeline, phase by phase — the same sequence we followed on a fully custom kitchen in East Cobb, Cobb County (30064) that our team designed, produced and installed end to end. For the full step-by-step story, see how our kitchen remodeling process works.

Before: a dated kitchen with oak cabinets at the start of a remodel
Day one of the timeline: a dated kitchen before anything is designed or built.

A realistic kitchen remodel timeline, phase by phase

Phase 1 — Home visit & measurements (first days).
You get in touch, we visit your home, see the space in person and take precise measurements — walls, ceiling height, windows, doors and every utility connection. This usually happens within the first week and takes a single visit.

Kitchen design materials and finish samples laid out during the design phase
Measurements and materials come first: a custom kitchen is built to the millimetre, so the design starts from the real room.

Phase 2 — Design, presentation & approval (about 1–3 weeks).
We design the new kitchen and present it to you with the render, the plan and examples of our previous projects. Together we select the materials. Nothing is produced until you approve the plan, the render, the quality, every detail and the price — that approval is the starting gun for the 6–10 week clock.

Phase 3 — Custom production (scheduled right after approval).
Your cabinets are manufactured to the approved design and your home's exact measurements. This is typically the longest single phase — and the quietest one for you: your old kitchen stays in place and fully usable the entire time.

Phase 4 — Demolition (a few days).
Only when the new kitchen is produced, packed and delivered does the old one come out. We protect the floors, remove the old cabinets, counters and appliances, and prepare the walls, plumbing and electrical for installation.

Kitchen under demolition during a remodel, cabinets removed and the room stripped back
Demolition starts only when the new kitchen is ready — the old kitchen out, the room stripped back.
Kitchen mid-renovation with the old flooring being removed
Old finishes out — flooring up, the room prepared for the new installation.

Phase 5 — Installation (with demolition, about 2–4 weeks total on site).
Cabinets, stone countertops, backsplash, fixtures and appliances are fitted to the design you approved. Because the same team designed and produced everything, pieces meet the room exactly as planned — no hand-offs between separate contractors.

New kitchen cabinets mid-installation during a remodel
Mid-installation: the new kitchen taking shape in the room.

Phase 6 — Final walkthrough & handover.
We walk the finished kitchen with you, detail by detail, and finish only when you are satisfied. From design approval to this moment: roughly 6–10 weeks for most full custom kitchens.

Finished bright luxury kitchen with a large island and crystal chandeliers
The end of the timeline: the finished kitchen at handover.
Completed white kitchen with marble countertops and an island with seating
The completed kitchen — designed, produced and installed by one team.

What takes the longest in a kitchen remodel?

Two things, typically. First, custom production: cabinets built to your room's exact measurements take longer than off-the-shelf boxes — that is the trade-off for a kitchen that actually fits. Second, decisions: the design, material and price approvals before production. Every week spent undecided before approval is a week added before the clock even starts.

Will I be without a kitchen the whole time?

No — and this is where the order of operations matters. At YK Development Group, demolition does not begin until your new kitchen has been produced and delivered. So during the design and production phases — most of the timeline — your existing kitchen works as normal. You are only without it during demolition and installation, roughly the final 2–4 weeks, and most clients set up a small temporary coffee-and-microwave corner for that stretch.

What causes delays in a kitchen remodel?

How can I avoid delays?

How our all-in-one process keeps the timeline tight

YK Development Group is a design-build remodeling company: we visit and measure, design, manufacture the cabinetry ourselves, demolish and install — design to production to installation, all in one, under one roof. That structure removes the two biggest timeline risks: waiting on third-party cabinet production, and demolition starting before the new kitchen exists. We build your vision. For the budget side of planning, see our Atlanta kitchen remodel cost guide and our kitchen remodeling in Atlanta page.

Kitchen remodel timeline — frequently asked questions

How long does kitchen demolition take?
For most kitchens, a few days: old cabinets, counters and appliances out, floors protected, and the room prepared for installation. In our process demolition only starts once the new kitchen is ready to come in.

How long does custom cabinet production take?
It depends on the scope and materials, and it is scheduled before demolition begins. It is typically the longest phase of a custom kitchen remodel — but it runs while your old kitchen is still fully usable.

Can I live in my home during a kitchen remodel?
Yes. Most clients stay in the home throughout. The disruptive part is limited to demolition and installation — about 2–4 weeks — when the kitchen itself is out of service; the rest of the house is unaffected.

When should I start if I want my kitchen ready by a certain date?
Count backwards: allow about 1–3 weeks for design and approval, then roughly 6–10 weeks from approval to handover. Starting the conversation about three months before your target date is a comfortable rule of thumb.

How do I start a kitchen remodel with YK Development Group?
Request a free estimate at developmentyk.com or call (470) 594-7666. We visit your home, measure, and present a design with a clear price — you approve the plan, the details and the price before anything is built.